Project Start Date: August 2019
Project Finish Date: July 2020
Project Value: $3.9 Million
Melbcon commenced construction at the new Edgars Creek Community Activity Centre in August 2019. The works involved the construction of a new community centre on a greenfield site and the facilities include – foyer and office area, maternal child health rooms, large meeting room with separate storage areas, staff room and IT services, three large kinder/ children’s rooms with their own bathroom and kitchen facilities, planning and storage rooms, other works included large car parking facilities, extensive external and landscaping works.
Architect: Croxon Ramsay
Client: Lendlease
Site Address: 55 Macedon Parade, Wollert [Access via Steen Avenue]
Project Contact: Michael Gekas – Project Manager, Lendlease